Study of the Operating Parameters of a Wind Power Plant with 0.75 MW Power under the Conditions of Tashkent Oblast
S. Q. ShoguchkarovTashkent State Technical University, Tashkent, UzbekistanTulqin JamolovTashkent State Technical University, Tashkent, UzbekistanN. Ye. MukhtarovTashkent State Technical University, Tashkent, UzbekistanI. A. YuldoshevTashkent State Technical University, Tashkent, Uzbekistan
ABI
Аннотация
Aspects of the use of the first experimental wind power plant with a capacity of 0.75 МW in the conditions of Tashkent oblast are considered. The results of monitoring of electric power development by the wind power plant for the months of 2017–2018 are presented. According to the monitoring data, the ratio of electric power production at the installation for the period from September 2017 to July 2018 was 714.9 МW h.